A design assessment was carried out in an effort to prevent potential premature bladed disk and impeller fatigue failures of three newly installed critical compressor trains.  Such a failure would result in a minimum five day pre-mature repair shutdown and cause over $15M (USD) in lost production revenue to the End User. 

A major Middle Eastern based petrochemical company required an expansion of an Ethylene plant to increase capacity of ethylene, linear low density polyethylene (LLDPE), and high density polyethylene (HDPE) by 2.8 million tons.  This expansion required four new steam turbine-driven compressor trains: the Cracked Gas Compressor (CGC), the Ethylene Refrigeration Compressor (ERC), the Propylene Refrigeration Compressor (PRC), and the C3 Splitter Heat Pump (C3S).  These trains included peripheral equipment including lubrication systems, anti-surge systems, valves, compressor control systems, and dry gas seal systems, all provided by foremost international manufacturers.  The End User realized that their $2.3 billion dollar investment might be jeopardized without the benefit of an independent assessment.  Therefore, such an assessment requirement was incorporated into the original equipment specifications.

 

Design Assessment Mitigates Risk

Example pre-construction assessment analysis of turbine blades.

Key assessment questions: Will the proposed compressor design achieve all expected operating conditions?  Will all compressor and turbine stages operate at the proposed speeds without degrading or catastrophic resonant vibration conditions?  Will the complete system, including auxiliary equipment, tolerate unusual and emergency operating situations without a failure?

MSI engineers were contracted by the End User and the Architect Engineering Company as third party design assessors to answer these and other questions.  During a typical assessment, MSI works very closely with the original equipment manufacturer (OEM).  Potential issues, and more importantly, solutions developed in concert with the OEM so that both the OEM and the End User benefits.  The results are reflected in the final equipment/system design and delivered machinery.

In this instance, the aerodynamic and thermodynamic performance of each compressor and turbine train was thoroughly evaluated.  The rotordynamics of each rotor system was analyzed for transient and steady-state torsional and lateral response.  Specific high risk compressor impellers and turbine blades were analyzed from a stress and vibrational point of view using highly detailed finite element analysis techniques (pictured above), fatigue Goodman Diagrams, and disk resonance Interference Diagrams.  Also, the complete dry gas seal and lubrication systems were thoroughly analyzed per API specifications and “Good Practice”.

The End User perceived the assessment as necessary and cost effective insurance to prevent potential catastrophic start-up problems, and to maximize reliability.  MSI’s analysis determined that one of the CGC HP compressor impeller stages needed a structural modification to address an impeller resonant condition and potential fatigue failure issue.  The manufacturer modified the impeller, thereby increasing the resonance separation margin from less than 1% to approximately 9%.  Such discussions were facilitated by MSI possessing German and Japanese speaking engineers on staff.  In general, by working in a positive fashion with the OEM’s, suggestions from all sides were implemented, with resulting improved equipment reliability.  An MSI Design Assessment provides peace of mind by reducing the risk associated with critical equipment start up and operation.

REAL-WORLD EXAMPLES AND CASE STUDIES

MSI In Action

Case Study

Improving Cost of Ownership with Vibration Risk Reduction: 1/2

Focusing on vibration and dynamics issues during the plant design phase of a project pays off with smoother commissioning and lower cost of ownership over the plant’s life.

Case Study

Simulating the Performance of a Spinal Implant

A manufacturer of an innovative spinal implant approached MSI for help in assessing the implant’s structural integrity.

Case Study

Dynamic Analysis of a Street Sweeper for the Manufacturer

Troubleshoot and identify potential opportunities for early bearing failure, MSI performed experimental modal analysis (EMA) and operational deflection shape (ODS) tests on a prototype unit for the manufacturer.